October Update: 4600 Regent Has a New Name.

Hundreds gathered to worship in the parking lot at 4600 Regent Blvd

October 2026

To every Future Is Now partner,

Before we ever opened the doors to our new home, hundreds of people showed up to worship in the parking lot. And that happened the same day our name finally went up on the building.

That moment felt like a preview. We were worshiping outside of what we have been praying, giving, and believing to one day worship inside. And I wanted you, as a partner, to see all of it in full detail, because you are the reason it is happening.

Before the Doors Opened, the Worship Began

On Thursday, October 8, the Awaken family gathered in the parking lot of our future home for an evening centered entirely on worship. People brought lawn chairs. A coffee cart rolled in. And with the new building standing right there as the backdrop, hundreds of people filled the lot to sing, pray, and thank God for what He is doing.

It was not a polished, tightly scripted service, and it was not meant to be. The worship team threw out the set list and simply followed where the Spirit led. It felt organic, open, and alive.

I have to be honest with you. Seeing that many people out in the lot was one of the most encouraging moments of this entire journey for me. For a long time, this has been concrete and steel and dollars and dates. That night, it was faces. It was families standing on the very ground where they will worship for years to come. It was the reminder of why we are building this.

A woman worshipping during Pop-Up Worship Night A group worshipping together at the future building

Before we worshiped inside our future home, we worshiped outside of it. Because the church was never the building. The church is the people who gathered in that lot.

Our Sign Is on the Building

The same day we worshiped in the lot, something else happened that made it all feel real. Our name went up on the building.

For months, this has been a construction site that could have belonged to anyone. Now, when you drive up to 4600 Regent, you see it clearly. This is Awaken Church. The monument signage and the building signage are in place, marking the spot our city will come to know. It is one thing to know the building is ours. It is another to see our name on the front of it.

New Awaken Church sign on the building New outdoor monument signage at 4600 Regent Blvd

We Built the Seats Ourselves

Back on Saturday, September 26, the Awaken family showed up for something we called Seats & Eats. The idea was simple. Breakfast, fellowship, and a few hours of rolling up our sleeves to assemble the chairs that will one day fill our new Worship Center.

No construction experience required. Just bring a drill or a screwdriver if you had one, and a willingness to serve. 45 people registered, gathered at 4600 Regent, and spent the morning building seating side by side.

Volunteers assembling chairs at Seats and Eats

Here is why it mattered. Those chairs are not just furniture. Every single one is a seat where someone will one day experience worship, hear the Word, encounter God, and find community. When you assemble a chair with your own hands, you are not just preparing a building. You are preparing a place for a person you have not met yet.

Seats & Eats was also the opening event of Closer ’26, our push to keep the Awaken family connected and engaged through this whole transition. It turned excitement into participation, and it let people put their hands directly on the future of this church.

We aren’t just preparing a building. We’re preparing a place for people, and we’re doing it together.

The Floors Are Going Down

If you have walked this journey with me long enough, you remember when these were just bare concrete slabs. Now the floors are becoming real.

The concrete floors are finished. Flooring is complete upstairs, and it is moving through the office and lobby spaces right now. The lobby flooring in particular is one of the first places you will walk when you step inside, and it is already transforming the feel of the entire entrance.

Detail of the new lobby flooring
New flooring being installed A worker finishing a lobby pillar next to the new flooring

The Room Where We’ll Gather

The biggest changes this month are happening inside the Worship Center.

First, a milestone worth celebrating. The Worship Center ceiling conduit is now 100% complete. Conduit is the network of protected pathways that carry all the power and the audio and video wiring across the ceiling. It is slow, tedious, mostly invisible work, and it has to be perfect before anything else can go up. Finishing it is a huge step.

Completed ceiling conduit and vent work in the Worship Center Ceiling conduit in the Worship Center

Second, and maybe the most exciting of all, the Worship Center platform is officially starting to take shape. The platform has been laid out, the conduit beneath it is more than halfway run, and steel is scheduled to go into the platform base. This is the stage. This is where worship will be led, where the Word will be preached, where thousands of moments will happen over the years. And now you can finally see it forming.

Pastor Ben walking through the new Worship Center Platform framing going in inside the Worship Center
Platform placement being installed

Every Space Is Moving

It is not just the Worship Center. Progress is happening everywhere you look.

More furniture has arrived. Restroom fixtures are going in, including the toilet fixtures in our children’s restrooms. Two aging rooftop HVAC units were removed and two brand-new units were set in place (those are the systems that heat and cool the whole building). The lobby ceiling grid and framing is complete. And in the children’s area, painting and finishes are underway.

Painting and finishes underway in the children's area

Completed in the Last 30 Days

ItemStatus
Worship Center ceiling conduit100% Complete
Worship Center platform laid outComplete
Furniture deliveredComplete
Concrete floor finishedComplete
Upstairs flooringComplete
Open office floorsComplete
Toilet fixtures in children’s restroomsInstalled
Lobby ceiling grid and framingComplete
Two new rooftop HVAC units set in placeComplete

Happening Right Now

ItemStatus
Platform conduit60% Complete
Steel for platform baseScheduled This Week
Light fixture installationThis Week
Lobby flooringInstalling This Week
Connecting rooftop HVAC to electric, gas, and building systemIn Progress
Tape and bedding in front-of-house areaIn Progress
Open office flooringIn Progress

Expected Over the Next 30 Days

ItemStatus
Pour platform concreteUpcoming
Pour ramp concreteUpcoming
Install door frames and Dutch doors for Champions roomsUpcoming
Complete flooring in back of houseUpcoming
Final paint in lobby and hallwaysUpcoming
Connect building automation system to all systemsUpcoming
Critical safety inspections (electrical, plumbing, HVAC, fire)Upcoming
Systems walk-through and trainingUpcoming
Obtain Temporary Certificate of Occupancy (TCO)Upcoming
Complete audio, video, and lighting (AVL)Upcoming

The Road to Opening the Doors

So what actually stands between us and walking in? A few big things, and I want you to understand them as clearly as I do.

Soon we move into lighting, final flooring and paint, and AVL completion. AVL is the audio, video, and lighting that makes a worship service possible. Then come the critical safety inspections for electrical, plumbing, HVAC, and fire suppression. These are the approvals that keep everyone safe and that the city requires before anyone can gather inside. Finally, we work toward the Temporary Certificate of Occupancy, or TCO, which is the official green light that legally allows us to open the doors and use the building.

That is the honest finish line. We are getting close.

November 1 Is a Huge Day

Before we get to opening, there is one moment I do not want you to miss. November 1 is a huge day in this story.

That Sunday, we are bringing a special Future Is Now Offering as we finish year one and step into year two of this campaign. Between now and then, I am asking every person and every family to pray, prepare, and ask God one simple question:

“What is my part?”

Sunday, November 1

The Future Is Now Offering

We finish year one and step into year two together. Take time before that Sunday to pray and prepare your part.

Learn About the Offering

Where We Stand

As partners, you deserve full clarity on where things stand.

Financial Update

as of October 14, 2026

Est. Project Cost – $7,234,032

Funds Set Aside From Sale – $1,250,000
Total Commitments – $3,433,195.50
Total Given – $1,280,856.57
Remaining Faith Target – $4,703,175.43

Let’s Finish the Wall

You already stepped in, and I am grateful for you. Here is what I am asking as we head into November 1.

  • If you’ve been giving faithfully, thank you. Stay faithful.
  • If you made a commitment but haven’t started, start.
  • If you haven’t made a commitment yet, it’s not too late.

On November 1, let’s come ready to finish the wall and walk into year two stronger than ever.

You can give to The Future Is Now at any time through any of the following ways:

Online:
Visit www.awakenchurch.ac/giving, tap Give, and select “The Future Is Now (Building)” fund.

Awaken Church App:
Open the app, select Irving as your location, tap Giving, and choose “The Future Is Now – Building.”

Text to Give:
Text “give” to 888.465.2275 and follow the prompts.

This month, we worshiped outside. Soon, we’ll worship inside. Awaken Church, The Future Is Now.

The Future Is Now.