Before we ever opened the doors to our new home, hundreds of people showed up to worship in the parking lot. And that happened the same day our name finally went up on the building.
That moment felt like a preview. We were worshiping outside of what we have been praying, giving, and believing to one day worship inside. And now, inside that building, the final pieces are starting to come together.
This update goes deeper than the video. If you want the full picture, every milestone, what it means, and what is coming next, this is it.
On Thursday, October 8, the Awaken family gathered in the parking lot of our future home for an evening centered entirely on worship. People brought lawn chairs. A coffee cart rolled in. And with the new building standing right there as the backdrop, hundreds of people filled the lot to sing, pray, and thank God for what He is doing.
It was not a polished, tightly scripted service. It was not meant to be. The worship team threw out the set list and simply followed where the night wanted to go. It felt organic, open, and alive.
And honestly, seeing that many people out in the lot was one of the most encouraging moments of this entire journey. For a long time, this project has been concrete and steel and dollars and dates. That night, it was faces. It was families standing on the very ground where they will worship for years to come. It was a reminder of what all of this has been for.
Before we worshiped inside our future home, we worshiped outside of it. Because the church was never the building. The church is the people who gathered in that lot.
The same day we worshiped in the lot, something else happened that made it all feel real. Our name went up on the building.
For months, this has been a construction site that could have belonged to anyone. Now, when you drive up to 4600 Regent, you see it clearly. This is Awaken Church. The exterior monument signage and the building signage are in place, marking the spot our city will come to know. It is one thing to know the building is ours. It is another to see our name on the front of it.
Back on Saturday, September 26, the Awaken family showed up for something we called Seats & Eats. The idea was simple. Breakfast, fellowship, and a few hours of rolling up our sleeves to assemble the chairs that will one day fill our new Worship Center.
No construction experience required. Just bring a drill or a screwdriver if you had one, and a willingness to serve. We gathered at 4600 Regent, and spent the morning building seating side by side.
Here is why it mattered. Those chairs are not just furniture. Every single one is a seat where someone will one day experience worship, hear the Word, encounter God, and find community. When you assemble a chair with your own hands, you are not just preparing a building. You are preparing a place for a person you have not met yet.
We aren’t just preparing a building. We’re preparing a place for people, and we’re doing it together.
If you have watched this journey long enough, you remember when these were just bare concrete slabs. Now the floors are becoming real.
The concrete floors are finished. Flooring is complete upstairs, and it is moving through the office and lobby spaces right now. The lobby flooring in particular is one of the first places you will walk when you step inside, and it is already transforming the feel of the entire entrance.
The biggest changes this month are happening inside the Worship Center.
First, a milestone worth celebrating. The Worship Center ceiling conduit is now 100% complete. If you are wondering what that means, conduit is the network of protected pathways that carry all the power and the audio and video wiring across the ceiling. It is slow, tedious, mostly invisible work, and it has to be perfect before anything else can go up. Finishing it is a huge step.
Second, and maybe the most exciting of all, the Worship Center platform is officially starting to take shape. The platform has been laid out, the conduit beneath it is more than halfway run, and steel is scheduled to go into the platform base. This is the stage. This is where worship will be led, where the Word will be preached, where thousands of moments will happen over the years. And now you can finally see it forming.
It is not just the Worship Center. Progress is happening everywhere you look.
More furniture has arrived. Restroom fixtures are going in, including the toilet fixtures in our children’s restrooms. Two aging rooftop HVAC units were removed and two brand-new units were set in place (those are the systems that heat and cool the whole building). The lobby ceiling grid and framing is complete. And in the children’s area, painting and finishes are underway.
| Item | Status |
|---|---|
| Worship Center ceiling conduit | 100% Complete |
| Worship Center platform laid out | Complete |
| Furniture delivered | Complete |
| Concrete floor finished | Complete |
| Upstairs flooring | Complete |
| Open office floors | Complete |
| Toilet fixtures in children’s restrooms | Installed |
| Lobby ceiling grid and framing | Complete |
| Two new rooftop HVAC units set in place | Complete |
| Item | Status |
|---|---|
| Platform conduit | 60% Complete |
| Steel for platform base | Scheduled This Week |
| Light fixture installation | This Week |
| Lobby flooring | Installing This Week |
| Connecting rooftop HVAC to electric, gas, and building system | In Progress |
| Tape and bedding in front-of-house area | In Progress |
| Open office flooring | In Progress |
| Item | Status |
|---|---|
| Pour platform concrete | Upcoming |
| Pour ramp concrete | Upcoming |
| Install door frames and Dutch doors for Champions rooms | Upcoming |
| Complete flooring in back of house | Upcoming |
| Final paint in lobby and hallways | Upcoming |
| Connect building automation system to all systems | Upcoming |
| Critical safety inspections (electrical, plumbing, HVAC, fire) | Upcoming |
| Systems walk-through and training | Upcoming |
| Obtain Temporary Certificate of Occupancy (TCO) | Upcoming |
| Complete audio, video, and lighting (AVL) | Upcoming |
So what actually stands between us and walking in? A few big things, and we want you to understand them.
Soon we move into lighting, final flooring and paint, and AVL completion. AVL is the audio, video, and lighting that makes a worship service possible. Then come the critical safety inspections for electrical, plumbing, HVAC, and fire suppression. These are the approvals that keep everyone safe and that the city requires before anyone can gather inside. Finally, we work toward the Temporary Certificate of Occupancy, or TCO, which is the official green light that legally allows us to open the doors and use the building.
That is the honest finish line. We are getting close.
Before we get to opening, there is one moment we do not want you to miss. November 1 is a huge day in this story.
That Sunday, we are bringing a special Future Is Now Offering as we finish year one and step into year two of this campaign. Between now and then, we are asking every person and every family to pray, prepare, and ask God one simple question:
“What is my part?”
Sunday, November 1
We finish year one and step into year two together. Take time before that Sunday to pray and prepare your part.
Learn About the OfferingFinancial Update
as of October 14, 2026
Est. Project Cost – $7,234,032
Here is where every one of us comes in.
On November 1, let’s come ready to finish the wall and walk into year two stronger than ever. You can give toward The Future Is Now or make a commitment at any time.
This month, we worshiped outside. Soon, we’ll worship inside. Awaken Church, The Future Is Now.
November 1. Pray, prepare, and ask God what your part is.
The Future Is Now Offering