Awaken Church, we have a May update for you and there is a lot to cover.

First, just thank you. Thank you for your faith through this process. Thank you for your flexibility. And thank you for continuing to show up while we build what God has next for this church. This has never just been about a building. It is about making room for people, for ministry, and for a future that is already coming into focus.

4600 Regent worship center interior, May 2026

We Are Still Here Through June

Here is some good news: nothing changes for you right now.

We have already moved our offices to a temporary location and have been preparing for transition but the buyer has graciously agreed to a leaseback arrangement, which means we get to stay longer than originally planned. We are still gathering at 4401 N. Highway 161 through the entire month of June. Sundays for main services. Wednesdays for youth. Same place, same schedule. Nothing changes for you right now.

We are moving forward month by month with September as our target move-in at 4600 Regent. That is the plan and we are building toward it every single day.

Pastor Ben walking the construction site at 4600 Regent

What Is Happening at Our Future Home

Real progress is happening. Here is what has been completed, what is happening now, and what is coming next broken down by area.

Worship Center The defining milestone of this month: a massive structural truss and beam has been installed. Cranes lifted steel into position after sections of the roof were removed and reinforced to handle the load. That is one of the most significant structural moments of this entire project. Right now, crews are actively installing metal wall studs around the perimeter of the worship center. Coming up next: rough electrical and HVAC installation.
Workers welding structural steel 4600 Regent Steel beam installation Awaken Church
Children’s Area This side of the building is moving fast. Walls are taped and bedded, rough electrical is complete, and concrete backfill for structural bracing is finished. Right now walls are being textured and primed. Next up: ceilings go in, and millwork and cabinetry for the kids’ spaces and front lobby are scheduled to arrive soon.
Outside the Building Landscape irrigation has been repaired, the main water shutoff has been replaced, and new metal studs have already been delivered and staged on site ready to go when the time comes.
Structural truss installed in worship center 4600 Regent

What used to exist only in drawings is becoming real walls and real rooms every single week.

Where We Stand

We want to be open with you about where The Future Is Now stands financially, because this is your church and you deserve to know.

Financial Snapshot May 2026
Sale funds
Given so far
Commitments
Funds from sale
$1,250,000
Given so far
$922,169
Commitments so far
$3,415,476
Faith target remaining
$2,568,556

Est. project cost $7,234,032

Commitments don’t build buildings. Dollars do. If you’ve made a commitment to TFIN, keep giving toward it consistently. And if you haven’t made a commitment yet now is the time. This is a two-year journey and we need you in it with us.

Every wall being framed. Every system being installed. Every inspection passed it is all happening because people like you are giving faithfully and consistently. Keep praying. Keep giving. Stay with us.

We are not waiting on the future anymore. We are building it. Together.

The Future Is Now.

Give to The Future Is Now at any time.